The Federal election was called on 28 March 2025. As this website is hosted by the Department of Infrastructure, Transport, Regional Development, Communications and the Arts, the site will only be updated with material in line with the Caretaker Conventions. Please note that the content of this site relates to the Australian Government’s existing policy.

2013/03—Jervis Bay Territory Water and wastewater services fees comparison table

2013/03—Proposed 2013 Fees for Water and Wastewater Services PDF: 52 KB

Annual Water Availability Fees

Pipe Size 2012 2013 Variance (%)
25mm $122.00 $127.00 4.10 %
32mm $200.00 $207.00 3.50 %
50mm $488.00 $506.00 3.69%
80mm $889.92 $1067.90 20%
100mm or more $1252.80 $1503.35 20%

Water Usage Fee

2012 2013 Variance (%)
Water Usage Fee (per KL) $0.86 $1.03 20%

Annual Wastewater Availability Fees

Pipe Size 2012 2013 Variance (%)
25mm $774.72 $929.65 20%
32mm $891.36 $1069.60 20%
50mm $1320.48 $1584.55 20%
80mm $2455.20 $2946.25 20%
100mm or more $3506.40 $4207.70 20%